Yangcheng Lake water project construction
Suzhou Industrial Park, second water source projects ( Yangcheng Lake water plant project phase ) in November 15, 2011 officially started, the construction scale of 200000 tons / day, the quality objectives for qualified, striving for excellent engineering, engineering for the duration of 372 calendar days. The main monomer having water intake pump house, with wells and the ozone contact tank, a flocculation sedimentation tank, a sand filter and carbon filter, suction well, two pumping station, waste water regulating pond, recycling pool, sludge thickening tank, auxiliary production workshop, liquid oxygen station, water pool. At present, a flocculation sedimentation tank, clear water basin earthwork excavation and the cushion construction is all over. At the same time the factory temporary sense already pouring completed, 3 tower cranes have been installed. Next, the earthwork comprehensive excavation and bracing of deep foundation pit operation.